Bridge Over Indian River
The Problem
The bridge is located on US-A1A near the City of Stuart, on the east coast of Florida.
It consists of thirty 102 ft. long simply supported spans. Each span consists of
five AASHTO Type III girders spaced at 5.5-ft. on centers with a 7 inch thick concrete
deck slab. The bridge opened to traffic in 1957 and was designed to carry two lanes
of AASHTO HS-15 loading.
All of the girders at the westernmost span exhibited severe signs of deterioration
due to saltwater spray caused by a seawall under the span at this location. Chloride
intrusion through the concrete resulted in corrosion of the bottom layer of strands
at several locations and spalling of the concrete cover resulted.
Close inspection of the condition of reinforcement revealed that the strands at
the bottom layer had lost over 50% of their cross section.
 |
|
|
Typical Spalling Caused by Corrosion |
Longitudinal View of Type III Girder |
Load testing evaluation revealed significant deterioration in the flexural capacity
of the span and required immediate attention. The level of deterioration was so
severe that replacement of the entire span was considered to be the only option.
The severity of the deterioration and the location of the bridge created an emergency
situation.
A high strength composite carbon laminate system was considered to be a valid solution.
The MAS2000 Fiber Wrap System provided the required strength and durability needed
for this application. The system was considered to be very economical when compared
to conventional and costly replacement methods. In addition, the system also serves
as a barrier protecting the girders from future contamination by saltwater spray.
The Solution
The MAS2000 Fiber Wrap System was designed to restore full capacity of the girders.
The damaged girders were first analyzed utilizing a non-linear finite element program
developed by SDR engineers. The program was developed and calibrated through extensive
laboratory and field testing and yields extremely accurate results. The results
of the analysis were used to design the optimum restoration solution.
Corroded portions of the prestressing strands were removed and a neutralizing agent
was applied to prevent future corrosion. The concrete sections were then restored
to original shape using high quality concrete capable of reaching full strength
within 24 hours. Girder restoration was followed by surface preparation according
to SDR specifications. A specially designed composite laminate was then applied
to the girders for their entire length.
The bridge, being located over water, presented a challenge to the work crew. However,
the repair was completed within 96 hours during a period of five days.
After completion of the repairs, surfaces of the girders were prepared and then
coated with a specially formulated polymer sealant to provide ultraviolet (UV) resistance
and to resist chloride intrusion.
The MAS2000 Fiber Wrap System proved to be economical, quick and easy to apply.
|
|
|
Application of MAS2000 Fiber Wrap System |
Rehabilitated Type III Girders |
Load testing and inspection proved the structure to be sound and the original load
rating for the bridge was maintained without any need for posting. Rehabilitation
was completed in 1997 and the bridge has been functioning without any signs of distress
or deterioration.
Back To Top